Florida Governor Declares State of Emergency for Tropical Storm Elsa

Bilzin Sumberg Publication
Client Alert
July 6, 2021
On July 3, 2021, through Executive Order 21-150, Governor DeSantis declared a state of emergency due to the threat of Tropical Storm Elsa in 15 counties, including Miami-Dade and Monroe County. Based on the Executive Order, certain development orders and building permits may be extended pursuant to Section 252.363, Florida Statutes.

Pursuant to the tolling and extension provisions of Section 252.363, Florida Statutes, the time for building permits and development orders may be tolled and extended for the sixty (60) days declared in the state of emergency, plus an additional six (6) months so long as the permit holder notifies the local government authority within ninety (90) days after the termination of the emergency declaration of the intent to exercise the tolling and extension afforded under the statute.

As the state of emergency was declared on July 3, 2021, if the state of emergency lasts 60 days, as currently indicated under the Executive Order, the deadline to notify the local government authority of the extension will be November 30, 2021. It is important to note, however, that the Governor has issued executive orders terminating the state of emergency for certain storms prior to the end of the 60 days, so we recommend monitoring the situation for additional executive orders which may change the anticipated deadline.

Bilzin Sumberg remains available to assist our clients in extending permits and otherwise preserving development rights. If you have any questions, please contact us.
RELATED PEOPLE
Brian S. Adler
Partner
Jennifer E. Fine
Associate
YOU MIGHT ALSO LIKE
Client Alert March 19, 2020
As a follow up to Bilzin Sumberg's Land Development & Government Relation's December 2019 Update regarding extensions of development orders and permits, this is a reminder that last year the Florida Legislature amended Section 252.363, Florida Statutes, to limit the ability to extend building pe...
New Miami Blog February 27, 2017
Developers must notify issuing governmental agency by July 10th to receive a new extension Holders of permits and development orders have the opportunity to toll the period remaining to exercise rights under the permit or order for nearly 16 months. Section 252.363 of the Florida Statutes permits a ...
Client Alert February 21, 2017
Interested parties must notify issuing governmental agency by July 10th to receive a new extensionIn Florida, holders of permits and development orders have the opportunity to toll the period remaining to exercise rights under the permit or order for nearly 16 months. Section 252.363 of the Florida...